Bypass Update – 14 March 2015

14 March 2015: The final shape of things at the end of Deep Spinney is clear – the kerbing is more or less completed, the new island kerbing is in place and the footpath is being reinstated.

Side walls at the entrances at both ends of the cycle underpass are being constructed and the underpass itself is being covered in preparation for the construction of the road over it. The section of bypass beyond has tarmac already in place.