12 December 2014: A mild December so far, and the race is on before the Xmas break (?).
The ‘cycleway underpass’ off the main entrance towards the ‘Baulk’ is progressing, and to the right hand side of the Baulk work is concentrating on the excavation/transfer of sand & gravel before the road foundation work can commence. The Clapham Road end site is also now established.
The Clapham Road end site is also now established.